Sheet 18Construction progress
The site, building by building, as the engineer certifies it
Every week the site reports its progress; the engineering firm that supervises the works checks and certifies it, and the technical control body gives its opinion at each stage. Certified stages trigger your calls for funds, never the reported progress.

Three phases, three moments of the works
- 1
Phase 1, west of the ravine
Lived in
Every home has been handed over.
- 2
Phase 2, along the boulevard
Handovers under way
7 buildings tracked · 98 % certified on average
Planned handover: 10/01/2027
- 3
Phase 3, east slope
On sale, works under way
10 buildings tracked · 18 % certified on average
Planned handover: 10/12/2028
Where each building stands
The solid bar is the certified progress, the light bar what the site reports, the tick what the schedule planned for today. Choose a building for its detail.
Certified by the engineerReported by the sitePlanned for today
Phase 3
- Building B615 %Under way: StructureShown below
- Building B743 %Under way: Building services
- Building B815 %Under way: Structure
- Building B915 %Under way: Structure
- Building B1015 %Under way: Structure
- Building B1115 %Under way: Structure
- Houses H3-A15 %Under way: Structure
- Houses H3-B15 %Under way: Structure
- Villas V3-A15 %Under way: Structure
- Villas V3-B15 %Under way: Structure
Building B6, stage by stage
The building's eleven stages, each in its planned window. Each column rises to the reported progress; the dark line marks what the engineer has certified.
- Certified
- 15 %
- Reported
- 22 %
- Planned today
- 23 %
- Current stage
- Structure
- EarthworksReported 100 % · Certified 100 %22/05/2026 → 01/07/2026
- FoundationsReported 100 % · Certified 100 %01/07/2026 → 13/08/2026
- StructureReported 24 % · Certified 0 %13/08/2026 → 12/07/2027
- MasonryReported 0 % · Certified 0 %12/07/2027 → 11/11/2027
- Building servicesReported 0 % · Certified 0 %11/11/2027 → 13/02/2028
- Façades and loggiasReported 0 % · Certified 0 %13/02/2028 → 28/04/2028
- FinishesReported 0 % · Certified 0 %28/04/2028 → 31/07/2028
- CompletionReported 0 % · Certified 0 %31/07/2028 → 07/09/2028
- LandscapingReported 0 % · Certified 0 %07/09/2028 → 15/10/2028
- TestsReported 0 % · Certified 0 %15/10/2028 → 12/11/2028
- HandoverReported 0 % · Certified 0 %12/11/2028 → 10/12/2028
The S-curve
Planned in dashes, reported by the site, certified by the engineer. Where the curves part, there is a question to ask.
Technical control opinions
The technical control body visits each building at its key stages and gives an opinion. The detailed remarks go to the site; an unfavourable opinion blocks the stage's certification.
Across the site
- B7 · MasonryFavourable06/11/2026
- B4 · HandoverFavourable20/10/2026
- H2-B · HandoverFavourable19/10/2026
- B11 · FoundationsFavourable29/09/2026
- B5 · CompletionFavourable with reservations28/09/2026
- H2-B · TestsFavourable28/09/2026
- B7 · StructureFavourable with reservations24/09/2026
- B3 · CompletionFavourable23/09/2026
Next visits
- B9 · Structure · 11/11/2026 at 10:00
- B10 · Structure · 15/11/2026 at 10:00
- B11 · Structure · 22/11/2026 at 10:00
Latest certificates on the site
- H2-B · Handover · 100 %22/10/2026
- B4 · Handover · 100 %22/10/2026
- B11 · Foundations · 15 %02/10/2026
- B5 · Completion · 92 %30/09/2026
- H2-B · Tests · 98 %28/09/2026
- B3 · Completion · 92 %27/09/2026
The site in pictures
The phase 3 site, photographed from the olive-tree park on a weekday morning.

Captures recorded for Building B6
- Site camera · Structure11/11/2026 11:00
- Site camera · Structure11/11/2026 08:00
- Drone · Structure03/11/2026 08:40
- Drone · Structure04/10/2026 08:40
- Drone · Structure06/09/2026 08:40
- Drone · Structure05/08/2026 08:40
- Drone · Structure06/07/2026 08:40
Mock-up Every month a drone flies over the site and fixed cameras photograph each building; each capture is recorded with its date and stage. In this demo the captures are recorded without their files: the photograph alongside shows the phase 3 site.